Select the four different techniques for planning projects.

CPM

Gantt Chart

AAA

PERT

CPA

CAQ

Apple graph

Why is it important to identify risks to the project as soon as possible?

To allow time to put solutions or contingencies in to place

To allow time for someone else to take over the budget

Why is regular and honest communication within the team important?

To ensure that everyone is still on track with their role towards the completion of the project

To make sure the team are all friends

What does the project management technique CPA mean?

Critical Path Analysis

Critical Points Addressed

Critical Points Analysis

Crucial Path Analysis