P3DBA1-3
Your Score: 0/4
Question 1 of 4
Select the four different techniques for planning projects.
CPM
Gantt Chart
AAA
PERT
CPA
CAQ
Apple graph
Why is it important to identify risks to the project as soon as possible?
To allow time to put solutions or contingencies in to place
To allow time for someone else to take over the budget
Why is regular and honest communication within the team important?
To ensure that everyone is still on track with their role towards the completion of the project
To make sure the team are all friends
What does the project management technique CPA mean?
Critical Path Analysis
Critical Points Addressed
Critical Points Analysis
Crucial Path Analysis
Quiz Complete!
You scored: 0 out of 4