Select the four different techniques for planning projects.
Gantt Chart
CAQ
Apple graph
AAA
CPA
PERT
CPM
Why is it important to identify risks to the project as soon as possible?
To allow time for someone else to take over the budget
To allow time to put solutions or contingencies in to place
Why is regular and honest communication within the team important?
To ensure that everyone is still on track with their role towards the completion of the project
To make sure the team are all friends
What does the project management technique CPA mean?
Crucial Path Analysis
Critical Points Analysis
Critical Path Analysis
Critical Points Addressed