P5DMALK15-1
Your Score: 0/5
Question 1 of 5
Match the words on the left with the items on the right.
Drag and Drop items from one side to pair them with items from the other side
Monitor / control
Execute / close
Planning
Evaluate the effectiveness of the project
Calculate the budget
Report on progress
Which three of the variables below can affect the viability of a project?
Gantt chart
Scope
Cost
Time
Quality
Is the following statement true or false? Cost is not always a determining factor when making project selections.
TRUE
FALSE
What is one of the purposes of a project implementation plan?
Identify timelines and sets expectations
Insufficiently prepare the project team
Staff training
Optimistic time estimates
Drag and drop the items into the correct order.
Drag and Drop items to re-order them
- Determine impact should it occur – red/amber/green
- Identify potential failure scenarios
- Determine likelihood – red/amber/green
- Secure support from management and key stakeholders
- Brainstorm potential scenarios
- Identify alternative suppliers, resources, and funding
Quiz Complete!
You scored: 0 out of 5