Your Score: 0/4

Question 1 of 4

What is one of the purposes of a project implementation plan?

Insufficiently prepare the project team

Staff training

Identify timelines and sets expectations

Optimistic time estimates

Which one of the below groups of people would not be involved in a project?

A representative of future users

Project sponsor

Project manager

A representative from a competitor

What technique can help you decide, quantitatively, whether to go ahead with a project?

Contingency planning

Finalising project plan

PBS and WBS

Cost-benefit analysis

Drag and drop the words into the correct gaps.

deliverablesresourcesrequirementsplan

The planning stage is the point at which you develop your management for the project. In your planning, you should be sure to capture the project , specific the quality of the , and make an informed estimate of and timescales.